Recoverable Depreciation
Also called: non-recoverable depreciation, depreciation holdback, withheld depreciation, less recoverable depreciation

Homeland Public Adjusters · Last reviewed: October 2026
Recoverable depreciation is the money your insurer withholds from a replacement-cost claim payment until you repair or replace the damaged property. The first check is actual cash value (replacement cost minus depreciation); the depreciation is “recoverable” because you get it back once the work is done and documented. Non-recoverable depreciation is depreciation the policy never pays back.
Enter the three totals from the bottom of the insurer’s estimate.
Illustration only. Your policy’s loss settlement clause and endorsements control; the estimate’s depreciation itself is often the number to dispute.
Full guide: What Is Recoverable Depreciation on an Insurance Claim?
What recoverable depreciation means
Most homeowners and many commercial policies pay losses at replacement cost value (RCV): the cost to repair or replace with materials of like kind and quality today. But the carrier does not hand over the full RCV up front. It first pays the actual cash value (ACV), which is RCV minus depreciation for age and wear, and holds back the difference. That difference is recoverable depreciation, also called the holdback or withheld depreciation.
Once you complete the repairs and send proof (invoices, a contractor’s final bill, photos), the carrier releases the holdback. If you never do the work, or never ask, the carrier keeps it.
How it is calculated
The adjuster’s estimate (usually written in Xactimate) depreciates each line item by its expected useful life. A 20-year architectural shingle roof that is 10 years old is depreciated roughly 50%; a 5-year-old interior paint job may be depreciated 50% or more; cabinets, flooring and drywall each carry their own schedule. The estimate then shows three totals: RCV, depreciation, and ACV. The depreciation column is what you are owed after repairs, less your deductible.
Recoverable vs. non-recoverable depreciation
Recoverable depreciation exists only on a replacement-cost policy. If your policy, or a specific coverage inside it, pays actual cash value only, the depreciation is non-recoverable: the carrier deducts it and never pays it back. The common places this happens are roofs under an ACV roof endorsement (see roof payment schedule), contents under a policy without replacement-cost contents coverage, detached structures on some forms, and older property on landlord (DP-1) policies. The estimate will say “non-recoverable” next to those lines. Check the declarations page before you accept that label; carriers apply it to lines that should be recoverable.
Florida
Florida law sets the order of payment. Under §627.7011(3)(a), on a dwelling claim the insurer “must initially pay at least the actual cash value of the insured loss, less any applicable deductible,” and must then “pay any remaining amounts necessary to perform such repairs as work is performed and expenses are incurred.” If the loss is a total loss, the insurer must pay replacement cost “without reservation or holdback of any depreciation in value.” For personal property, §627.7011(3)(b) lets the insurer pay ACV first and the rest against receipts, up to the policy limit.
Two things follow from that. First, the holdback is not a settlement: it is money the statute says you are owed as the work progresses, so you do not have to finish the whole job before asking for the first release. Second, a carrier that depreciates labor, or depreciates an item with no meaningful useful-life schedule (a slab, a tear-out, a code upgrade), is reducing the ACV payment below what the statute requires.
New Jersey
New Jersey has no statute on the order of replacement-cost payments; the policy language controls. Standard forms pay ACV until repair or replacement is complete and then pay the difference, usually with a time limit (commonly 180 days or one year from the loss, or from the ACV payment) to make the claim for the holdback. Read the loss settlement clause for the exact window; missing it is the most common reason New Jersey policyholders lose the holdback. Claim-handling timing is governed by N.J.A.C. 11:2-17.7, which requires the insurer to accept or deny within 30 calendar days of a properly executed proof of loss and to explain delays in writing every 45 days.
How carriers use it against you
- Letting the clock run. Many policies require you to complete repairs within a stated period to recover the holdback. Carriers rarely remind you.
- Depreciating labor and non-wearing items. Labor does not age. Neither does a tear-out or a dumpster. Depreciation belongs on materials with a useful life.
- Calling it non-recoverable. An ACV roof endorsement applies to the roof surfacing, not to the decking, the interior water damage or the contents.
- Releasing it only against the carrier’s estimate. If the real repair cost more than the carrier estimated, that is a supplemental claim (see supplemental claim), not a reason to cap the holdback.
- Paying the holdback to a contractor. Unless you signed a direction to pay, the holdback is owed to you.
Worked example
Roof replacement, RCV $38,000. The roof is 12 years into a 25-year life, so the estimate depreciates the shingles and underlayment by 48%, about $14,400 of the $30,000 in materials; labor and tear-off are not depreciated. Deductible $2,500. First check: $38,000 − $14,400 − $2,500 = $21,100. After the roof is replaced and the invoice submitted: $14,400 recoverable depreciation released. Total paid: $35,500, which is the RCV less the deductible. If the policy had an ACV roof endorsement, the $14,400 would be non-recoverable and the claim would end at $21,100.
Use the calculator above to run your own numbers from the estimate’s RCV, depreciation and deductible lines.
Frequently asked questions
How do I get my recoverable depreciation back?
Is there a deadline to claim recoverable depreciation?
Can I keep the recoverable depreciation if I do the work myself?
Why is depreciation on my estimate so high?
Related terms
Replacement cost value (RCV) is what it costs to repair or replace damaged property with new materials of like kind and quality today.
A roof payment schedule (roof surfacing payment schedule) is a policy endorsement that pays a roof loss at a percentage of replacement cost set by the roof's age and material, instead of full…
A supplemental claim is a claim for additional loss or damage from the same peril the insurer has already adjusted, or for costs incurred while repairing under an open claim.
Overhead and profit (O&P) is the general contractor's charge for running the job: overhead is the cost of doing business (office, insurance, supervision, permits), and profit is the margin.
If this is your loss, call Homeland before you talk to the insurance company: Florida (305) 783-3777, New Jersey (732) 517-3777, 24 hours. A licensed public adjuster reviews the claim for free and calls you back right away. No Recovery, No Fee.
Sources
This article is for general information only and is not legal or insurance advice. Statutes, regulations and policy wording change, and how they apply depends on your own policy and the facts of your claim. Homeland Public Adjusters is a public adjusting firm, not a law firm.
- Surprising Things Your Policy Covers
- Neighbor's Condo Fire: Who Pays?
- Damaged Tile or Laminate: A Claim?
- Barn, Stable & Outbuilding Coverage
- Wind and Tornado Risk on the Farm
- Crop Insurance vs. Property Insurance
Upload the denial letter or the insurer’s estimate. A licensed public adjuster reads it and calls you back right away. Free.
Free Claim Review